2005-064 NLB Change Order Taycon ConstructionRESOLUTION 64-2005
A RESOLUTION OF THE VILLAGE COUNCIL OF THE VILLAGE OF NORTH PALM
BEACH, FLORIDA, ON BEHALF OF THE VILLAGE OF NORTH PALM BEACH AND AS
AGENT FOR THE NORTHLAKE BOULEVARD TASK FORCE, AUTHORIZING A
CHANGE ORDER WITH TAYCON CONSTRUCTION MANAGEMENT, INC., FOR
PHASE I STREETSCAPE PROJECT FOR THE NORTHLAKE BOULEVARD CORRIDOR
ATTACHED AS EXHIBIT "A"; AND, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the Village Council awarded a bid and entered into a contract in the amount of
Three Hundred Twenty-five Thousand Six Hundred Seventy ($325,670.00) Dollars with Taycon
Construction Management, Inc., to implement the Phase I Streetscape Project for the Northlake
Boulevard corridor; and
WHEREAS, the original bid and contract with Taycon Construction Management, Inc., did not
include the Lake Park side of the Northlake Streetscape Project; and
WHEREAS, the change order attached as Exhibit "A" includes the Lake Park area together with
alternates in the amount of Two Hundred Ten Thousand Four Hundred Forty-eight
($210,448.00) Dollars, which brings the contract price to Five Hundred Thirty-six Thousand One
Hundred Eighteen ($536,118.00) Dollars; and
WHEREAS, the Northlake Boulevard Task Force, at its meeting on July 18, 2005, unanimously
voted to recommend that the Village Council approve the change order.
BE IT RESOLVED BY THE VILLAGE COUNCIL OF NORTH PALM BEACH, FLORIDA:
Section 1. The Village Council of the Village of North Palm Beach, Florida, on behalf of the
Village of North Palm Beach and as agent for the Northlake Boulevard Task Force, does hereby
approve a change order with Taycon Construction Management, Inc., for Phase I Streetscape
Project for the Northlake Boulevard corridor attached as Exhibit "A", with- the funding to come
from Palm Beach County and additional funds from the Northlake Boulevard Task Force.
Section 2. This resolution shall take effect immediately upon its adoption.
PASSED AND ADOPTED THIS 4th DAY OF AUGUST, 2005.
ATTEST:
VILLAGE CLER
NOR"I'HLAKE TASK FORCE CHANGE ORDER -ADD LAKE PARK 07-14-OS
Adjustments to Taycon Proposal dated 7 June 2005
Landscape Total 73,596
2. Substitute Sweet Bay - 59 x $842.40=$49,701.60. vs $60,133. -10,431.
6. Ligustrum - no change- Taycon error- 72x10.53=758 -758.
7. Plumbago-no change-Taycon error- 435x9.36=4,072. - 4,072.
17. Bio Barrier-error-256 vs 56 = 200x7.80 +1,560.
New Landscape total 59,895.
Paving total 95,001.
Demolition total 26,138
Irrigation total 16,348
Misc total 35,877
Total Lake Park side 233,259
Total NPB as bid 325,670
TOTAL 558.929.
Substitute Sweet Bay Magnolia #2 as bid
46 x $702=32,292 vs 37,674 as bid -5,382
Substitute Alternate #35 -Jack & Bore -4,320
12,960 vs 17,80 as bid
TOTAL 549,227.
Delete 12 Sweet Bay Magnolia (Behind S/W LP) 842.40x17_ -10,109
#20 Adjust Sidewalk Pressure clean -3,000
TOTAL CONTRACT PRICE PROPOSED $536,118
Less bid price previously awarded 325,670.
NET CHANGE ORDER TO BE ISSUED $210,448.
This proposed change order is the agreed to adjustments to Taycon Construction proposed
change order which is attachment A that is based on Redd and Asso. quantities.
NLTF CHANGE ORDER PROPOSED #3 07-18-OS
Northlake Streetscape Project
Change Propose No. 1
ADD Lake Park Portion t c of Wot~k
NpIUtl0k0 Boulev9rd StrCetncnpe - Phdsa ~
NOrttt Pe{T e8A0h ! Leka PB*k, Flprlde
PRELIMINARY
SUBMITTED June i, 2005
SECTION 16: SCHEDULE OF CHANGE ITEMS -LAKE PARK PORTION
~Nenir_~ pRnPf~~AI (TENS Per MR
sip otzoos
i
~~`-~'~-
~~~
I ~~
Change kem No. Unk Quantity Unit Cost total Cost
Candace In
1 Pi eon Plum ee. 0 #DN/01 $ -
2 LItUe Gem Ma nol,a ee. 59 $ 1 019.20 $ _ 60,133
3 Ti Plant ea. 0 f#DIV/0! $ -
4 S Ider Li ea. 4 $ 9.36 S 37
5 Coco um ea, 40 S 9.36 $ 374
8 L' ustrum Hed a ea. 72 $ ~ 0.53 $ 756
7 Plumba o ea. 435 $ 9.36 $ 4,072
8 Dwarf Crown of Thorns ea. 0 #DIV/0! S -
9 Green Island Flcus ea. 0 #DIV101 $ -
10 Da L;1 ea. 30 S 4.se $ 140
1 t Lino a ea. 633 $ 3.51 $ 2,222
12 Confederate Jasmine ea. 82 $ 4.68 $ 290
13 Sod si. 2 275 $ 0.33 $ 151
14 Mulch 3" Maleuca c 0 #DIV/01 $ -
15 !anti SoN 1 Fertilizer Is. 0 #DIV/01 $ -
1fi Root Barrier if. 312 $ 14.04 $ 4,381
17 Bio Banter if. 56 $ 7.80 $ 437
Landscape Subtotal S 73 595
Per MR
Change Item No. Unit Quantity Unit Cost Total Cost
Paving
t8 4"Thick Concrete Sidewalk-Median sf. o #DN/O! $ -
19 E Concrete -Median sf. 0 #DIV/0! $ -
20 Sidewalk Pressure Clean 8 V .Removal Is. 1 $ 6,397.58 $ 6.398
21 O en cut Conc. A ron Re ur and Re air H. 0 #DIV/01 $ -
22 Undistributed Concrete Re air sf. 0 tXDN10! $ -
23 Tree Grates with Frame ea. 45 $ 1,968.97 $ 88 604
Paving Subtotal S 95 001
Pwr Herz
Change Item No. Unit Quantity Unk Cost Total Cost
DemollUon
24 Removal of ExiStin Sidewalk s1. 6,678 $ 3.00 $ 20,002
25 Saw-cut Existin Pavement Sidewalks If. 1,907 $ 3.22 $ 6,136
26 emoval of Exis6n SBbal Palms Is. 0 #DIV/0! $ -
27 Removal of Exis6n Landsca In ts. U #DIV/01 S -
Demolitlon Subtohl 26 138
TAYCf3N Construction Management, Inc. Page 1 of 3
Northlake Streetscape Project
Change Proposal No, l
A,pD Lake Park Portion to Scope of Work
NorlMake Boulevard StreetsCapo • Dhaee 1
NWth PeiM B98~n ! L9k9 Park, Florida
5 JBMIT7ED Juns 7. 2005
SECTION 16: SCHEDULE OF CHANGE ITEMS -LAKE PARK PORTION
rt-ae~IrG PRf~PCI~AI ITFMS
Unit Quantity
Change ttem No Unlt Cost Total Cost
.
IM anon Per MR
28 6" Po U S Heads ea 172 $ 28.08 $ 4,830
29 1-1l2' Electric Control Valve Confi ea. 12 $ 263.25 $ 3,159
30 Rafnblyd ESP 12 Station Controller ea. 0 #DIV/0! S -
31 Minf click ain Sensor ea. 0 #DIVIO! $ -
32 1-112" Gate Valve Isolation ea. 0 #DIV10! $ -
33 1-1/2"SCH.40 Main line H. 600 $ 2.48 $ 1,474
a4 ~„~i W;dn Is. 1 $ 2,808.00 $ 2 808
35 Jack and Bore If. 0 #DIV/0! $ -
36 S1eev1 Is. 1 $ 4 077.45 $ 4,077
37 1" Irri anon Meter and Backflow Prevention ea. 0 #OfV/0! $
38 120 -Volt hand-held power supply service -
Considers electric service is existing Q ROW
line
ea
0
#DIV/01
$ -
Irrfgatlen Subtotal S 16,348
Pwr MR
Change Ftern No. Unit Quantity Unit Cost Total Cost
Mlscetianeous
37 Maintenance of Traffic M07 !s. 1 $ 7,465.77 $ 7,466
38 Mobll!zation, 9onds, Insurance 8 OH 8 P ~
13 % Reduced from 14%
15.
1
$ 28,411.24
$ 28,411
39 elocate of Existing Tra is Sign on New
Traffic Pole MUTCD R1-1
ea.
0
#DIV/0!
$ -
40 Relocate of Existing Stop Sign on New
Traffic Pole MUTCD R1-1 30" x 30"
ea.
0
#DIVl01
$ -
Mlscellaneous Subtotal S 35,877
SECTION 16' SCHEDULE OF CHANGE ITEMS -LAKE PARK PORTION
Change Proposal No. 1
Subtotals Total Gost
Landsca In $ 73 595
Davin $ 95 001
Demolition $ 26,138
Irri anon 16 348
Miscellaneous $ 35,877
611412405
Total $ 246,960
Time Extension Requi~sd for Above -Forty Flve (45) days
TAYCON Construction Management, Inc, Page 2 of 3
Northlake Streetscape Project 6110/2005
Change Proposal No. l
A,DD Lake Park Portion to Scope of Work
NortNake Bpule+v9rd Streetacape -Phase t
NOftl'1 P91m t3eeCh I l.Ake Park, FIOrMB
,ppq June 7.2008
SECTION 'S8: SCHEDULE OF CHANGE fTEMS
SUBSTITUTE CHANGE PROPOSAL ITEMS
Item No. Item
Unft
3 Red Fountain Grass ea. 0 ~Dlv/0! $ -
6 Sim on's Sto er ea. 0 #DIV/0! $ -
25 Removed: Not a livable tf '-
35 Directional Bore for 1.5" Im ation mainline tf. 380 $ 18.00 $ 6,840.00
ADD-ALTERNATIVE
CHANGE ITEMS - NPB
MEDIAN ~ LAKE PARK
A
Item Na. Item
Unit
42 Benches ea. 6 $ 2,683.75 $ '16,162,50
43 Trash Receptacles ea. 6 $ 1,400.00 $ 8,400.00
44 Streetsvape Icons ea. 6 fi,062.50 $ 36,375.00
TAYCON Construction Managerr~ent, Inc. Page 3 of 3