2006-051 Change Orders with Taycon NLB. Phase 1 StreetscapeRESOLUTION 2006-51
A RESOLUTION OF THE VILLAGE COUNCIL OF THE VILLAGE OF NORTH PALM
BEACH, FLORIDA, ON BEHALF OF THE VILLAGE OF NORTH PALM BEACH AND AS
AGENT FOR THE NORTHLAKE BOULEVARD TASK FORCE, AUTHORIZING CHANGE
ORDERS WITH TAYCON CONSTRUCTION MANAGEMENT, INC., FOR PHASE I
STREETSCAPE PROJECT FOR THE NORTHLAKE BOULEVARD CORRIDOR
ATTACHED AS EXHIBIT "A"; AND, PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the Village Council awarded a bid and entered into a contract in the amount of
Three Hundred Twenty-five Thousand Six Hundred Seventy ($325,670.00) Dollars with Taycon
Construction Management, Inc., to implement the Phase I Streetscape Project for the Northlake
Boulevard corridor; and
WHEREAS, the original bid and contract with Taycon Construction Management, Inc., did not
include the Lake Park side of the Northlake Streetscape Project; and a change order was
authorized and approved to include the Lake Park area together with alternates in the amount of
Two Hundred Ten Thousand Four Hundred Forty-eight ($210,448.00) Dollars, which brings the
contract price to Five Hundred Thirty-six Thousand One Hundred Eighteen ($536,118.00)
Dollars; and
WHEREAS, the change orders (CO #1 & CO #3) attached as Exhibit "A" provide for additional
expenditures of Four Thousand One Hundred and Eighty-five ($4,185.00) Dollars and Three
Thousand Seven Hundred and Fifty ($3,750.00) Dollars respectively for costs associated with the
planting of 31 East Palatka Holly trees and 19 Magnolia trees, completing the streetscape project,
Phase 1; and
WHEREAS, the Northlake Boulevard Task Force, at its meeting on June 26, 2006, voted to
recommend that the Village Council approve the change orders.
BE IT RESOLVED BY THE VILLAGE COUNCIL OF NORTH PALM BEACH, FLORIDA:
Section 1. The Village Council of the Village of North Palm Beach, Florida, on behalf of the
Village of North Palm Beach and as agent for the Northlake Boulevard Task Force, does hereby
approve change orders with Taycon Construction Management, Inc., for Phase I Streetscape
Project for the Northlake Boulevard corridor attached as Exhibit "A", with the funding to come
from Northlake Task Force, Northlake Boulevard project account with a fund balance of
$53,916.29.
Section 2. This resolution shall take effect immediately upon its adoption.
PASSED AND ADOPTED THIS 13th DAY
ATTEST:
~~~ ~iZ2~
VILLAGE CLERK
NORTHLAKE BOULEVARD
CONSTRUCTION CHANGE PROPOSAL (CCP)
T0: The Village of North Pam Beach CCP NUMBER: ONE (1)
501 U.S. Highway One DATE: 6/26/2006
North Palm Beach,FL 33408 PROJECT NAME: Northlake Streetscape
ATTENTION: Mr. Wiley Livingston PROJECT NUMBER: 227
CONTRACT NUMBER:
REFERENCE: Modifications to the contract as
described below.
We propose to accomplish the MODIFICATIONS identified in the field and as described herein. Except as modified below, the
original contract and all prior amendments shall remain in full force and effect:
DESCRIPTION: Change 31 Pigeon Plums as per plan to East Palatka
Hollies.
REASON: Lack of availability caused by limited supply after
Hurricane Wilma
PROPOSED CONTRACT PRICE CHANGE (increases) $ 4,185
(decrease)
(unchanged)
PROPOSED CONTRACT TIME CHANGE (increases)
(unchanged)
PROPOSED NEW SUBSTANTIAL COMPLETION
T0: Village of North Palm Beach FROM: Taycon Construction Management, Inc.
OWNER CONTRACTOR
SIGNED: SIGNED:
Date: Date:
NORTHLAKE BOULEVARD
CONSTRUCTION CHANGE PROPOSAL (CCP)
T0: The Village of North Pam Beach CCP NUMBER: THREE (3)
501 U.S. Highway One DATE: 6/26/2006
North Palm Beach,FL 33408 PROJECT NAME: Northlake Streetscape
ATTENTION: Mr. Wiley Livingston PROJECT NUMBER: 227
CONTRACT NUMBER:
REFERENCE: Modifications to the contract as
described below.
We propose to accomplish the MODIFICATIONS identified in the field and as described herein. Except as modified below, the
original contract and all prior amendments shall remain in full force and effect:
DESCRIPTION: Deliver to the project the remaining 19 Magnolia trees
and plant five (5) on the property at 309 Northlake Boulevard
and seven (7) at 401 Northlake Boulevard in accordance with
plan by Michael Redd & Associates, P.A. labeled LP Phase I
and dated 02107106. Seven (7) remaining trees to be planted
at other Village location
REASON: Owners request
LUMP SUM BREAKDOWN: Delivery charge and Landscaper re-mobilization 1,400.00
Irrigation material, installation and re-mobilization 1,070.00
Taycon extended General Conditions 800.00
Clean up and Protection 400.00
Bonds and Insurance 80.00
TOTAL 3,750.00
PROPOSED CONTRACT PRICE CHANGE (increases) $ 3,750
(decrease)
(unchanged)
PROPOSED CONTRACT TIME CHANGE (increases) 45 DAYS
(unchanged)
PROPOSED NEW SUBSTANTIAL COMPLETION
T0: Village of North Palm Beach FROM: Taycon Construction Management, Inc .
OWNER CONTRACTOR
SIGNED: SIGNED:
Date: Date: