Capital Improvements PlanFY 2015 Proposed Budget Page 230 of 297
Capital Improvement Plan
INTRODUCTION
Municipal government provides needed and desired services to the
public and in order to provide these services, the Village must
furnish and maintain capital facilities and equipment. This is
accomplished through the use of a Capital Improvement Plan (CIP).
The CIP is a five year projection of future improvements to existing
facilities, the acquisition of land and buildings, construction of new
facilities and major equipment purchases. This includes the regular
replacement of equipment such as vehicles and computer
hardware /software. The Village Council adopts the five year plan as
a part of the annual budgeting process. The first year of the plan is
the only year for which funding is authorized. The remaining
four years of the CIP lists the capital proiects that will be done in
the future and their estimated cost ... funding requirements are
identified, but are not authorized.
The Village of North Palm Beach defines a "capital outlay" as the
cost(s) associated with the acquisition of land, land improvements,
buildings, building improvements, construction in progress,
machinery and equipment, vehicles and infrastructure, and other
tangible or intangible assets that are used in operations and that have
an initial useful life extending beyond a single reporting period.
Capital assets and infrastructure are capitalized and depreciated as
outlined in the capitalization table below:
Capitalization Threshold Table:
The plan places projects in priority order, and schedules the projects
for funding and implementation. As presented, it is a five -year
forecast that allows the Village to plan ahead for its new capital and
renewal and replacement needs.
Programming capital requirements over time can promote better use
of the Village's financial resources, reduce costs and assist in the
coordination of public and private development. Careful
management of its assets keeps the Village poised for flexible and
responsive strategic planning that allows the Village to proactively
prepare the groundwork for capital projects so when funding
opportunities arise, a plan is ready to be implemented. By looking
beyond year -to -year budgeting and projecting what, where, when
and how capital investments should be made, capital planning
enables the Village to maintain an effective level of service for the
present and future population.
FY 2015 Proposed Budget Page 231 of 297
Capitalize and Depreciate
Land
Capitalize only
Land improvements
$25,000
Building
$50,000
Building Improvements
$50,000
Construction in Progress
Capitalize only
Machinery & Equipment
$5,000
Vehicle
$5,000
Infrastructure
$250,000
The plan places projects in priority order, and schedules the projects
for funding and implementation. As presented, it is a five -year
forecast that allows the Village to plan ahead for its new capital and
renewal and replacement needs.
Programming capital requirements over time can promote better use
of the Village's financial resources, reduce costs and assist in the
coordination of public and private development. Careful
management of its assets keeps the Village poised for flexible and
responsive strategic planning that allows the Village to proactively
prepare the groundwork for capital projects so when funding
opportunities arise, a plan is ready to be implemented. By looking
beyond year -to -year budgeting and projecting what, where, when
and how capital investments should be made, capital planning
enables the Village to maintain an effective level of service for the
present and future population.
FY 2015 Proposed Budget Page 231 of 297
THE CAPITAL IMPROVEMENT PLAN (CIP)
The result of this continuing planning process is the CIP, which is
the Village's five -year roadmap for creating, maintaining, and
funding present and future capital requirements. The CIP serves as a
planning instrument in conjunction with the Village Comprehensive
Plan and the Village Council's Goals to identify needed capital
projects and coordinate the financing and timing of improvements in
a way that maximizes the return to the public. It provides a planned
systematic approach to utilizing the Village financial resources in the
most responsive and efficient manner to meet its service and facility
needs. It serves as the "blueprint" for the future of the community
and is a management and planning tool.
The underlying strategy of the CIP is to plan for capital expenditures
necessary for the safe and efficient provision of public services in
accordance with Village policies and objectives adopted in the
Village's Comprehensive Plan. It involves conducting needs
assessments and allowing for flexibility to take advantage of
opportunities for capital investment. Capital planning decisions are
made based on an analysis of each project which includes: cost
versus benefits, capital renewal strategies, repair- versus - replacement
costs and new service demands. A critical element of a balanced
CIP is the provision of funds to both preserve or enhance existing
facilities and provide new assets to respond to changing service
needs.
While the program serves as the long range plan, it is reviewed and
revised annually in conjunction with the budget. Projects and their
scopes are subject to change as the needs of the community become
more defined and projects move closer to final implementation.
Priorities may be changed due to funding opportunities or
circumstances that cause a more rapid deterioration of an asset.
Projects may be revised for significant costing variances.
The adoption of the CIP is neither a commitment to a particular
project nor a limitation to a particular cost. As a basic tool for
scheduling anticipated capital projects, it is a key element in
planning and controlling future capital financing. When adopted, the
CIP provides the framework for the Village's management team and
the Village Council with respect to investment planning, project
planning and managing any debt.
CIP REVIEW
The Village Manager is responsible for reviewing capital project
requests and providing recommendations to the Village Council.
Each department submits requests for its capital funding
requirements to the Village Manager. These requests could be for
something as minor as the purchase of a piece of equipment to the
complete rebuild /new installation of a piece of infrastructure.
The Village Manager, along with the Finance Director and
Department Head, conduct an in -depth analysis of the impact of the
CIP on cash flow and financial obligations, as well as the Village's
ability to finance, process, design and ultimately maintain projects.
The fiscal impact for each individual project (including future
maintenance and replacement costs), is also analyzed. The overall
goal is to develop CIP recommendations that:
FY 2015 Proposed Budget Page 232 of 297
• Preserve the past, by investing in the continued upgrade of
Village assets and infrastructure;
• Protect the present with improvements to Village facilities
and infrastructure;
• Plan for the future.
CIP CRITERIA & CATEGORIES
The CIP is developed through input by professional staff, citizens of
North Palm Beach, and elected Village officials. There are typically
more proposals than can be funded in the five -year CIP period, so
the projects are evaluated and ranked in order of priority according
to the following guidelines:
a) Whether the proposed project is financially feasible, in terms
of its impact upon Village budget potential;
b) Whether the project is needed to protect public health and
safety, to fulfill the Village's legal commitment to provide
facilities and services, or to preserve, achieve full use of, or
increase the efficiency of existing facilities;
c) Whether the project represents a logical extension of
facilities and services within a designated Village Planning
Area; and
d) Whether or not the proposed project is consistent with plans
of State agencies and the South Florida Water Management.
Further, the projects are broken down into the following categories:
1. The project is urgent and /or mandated, and must be
completed quickly. The Village could face severe
consequences if the project is delayed, possibly impacting the
public health, safety, and welfare of the community, or
having a significant impact on the financial well being of the
Village. The project must be initiated or
financial /opportunity losses will result.
2. The project is important and addressing it is necessary. The
project impacts safety, law enforcement, public health,
welfare, economic base, and /or quality of life in the
community.
3. The project would enhance the quality of life and would
provide a benefit to the community. Completion of the
project would improve the community providing cultural,
recreational, and /or aesthetic effects.
4. The project would be an improvement to the community, but
need not be completed within a five -year CIP.
Based on the criteria and category, the project is either included in
the CIP or excluded.
CIP POLICIES
• The Village will adopt the first year of a multi -year plan for
capital improvements, update it annually and make every
attempt to complete all capital improvements in accordance
with the plan.
• The Village will coordinate the development of the CIP
budget with the development of the operating budget to
ensure future operating expenditures and revenues associated
with new capital improvements will be projected and
incorporated into the current and future operating budgets.
FY 2015 Proposed Budget Page 233 of 297
• The Village will maintain its physical assets at a level
adequate to protect the Village's capital investment and
minimize future maintenance and replacement costs.
• In making or providing of capital improvements, The Village
shall not incur a general obligation debt requiring the full
faith and credit and taxing power of the Village that exceeds
five (5 %) of the property tax base of the Village. For Fiscal
Year 2015, this amounts to $80.45 million. The Village has
no general obligation debt.
CIP FINANCING/FUNDING ALTERNATIVES
Capital improvements may be funded by a variety of means
depending on the nature of the project, availability of funds, and the
policies of Village Council. Financing decisions are made based on
established Village policies and available financing options directly
related to project timing and choice of revenue sources. The funding
methodology for the CIP is reliant upon available resources
including regular operating funds, funds from grants and user fees,
useful life of the improvement, and sharing the costs between current
and future users. While some projects can be delayed until funds
from existing revenues are available, others cannot. The Village
explores all options such as ad valorem taxes, grants, developer
contributions, user fees, bonds, loans, and undesignated reserves to
fund improvements. The following financing sources are available
to fund the CIP:
• Ad Valorem Taxes: The Village does not use these funds as a
debt security due largely to the required electoral approval
(voter referendum) prior to issuance. Property taxes are
directly linked to the assessed value of individual property,
not to the consumption of specific goods and services.
• Non -Ad Valorem Revenues: These types of revenues can be
pledged to support various types of bond issues. Such bonds
are similar to general obligation bonds in that proceeds are
often used for general government purposes and repayment is
unrelated to the revenue generating capacity of the project
being financed. However, unlike general obligation bonds,
non -ad valorem revenue bonds are payable solely from
revenues derived from the pledged revenue (such as sales tax,
local option fuel tax, and the guaranteed portion of municipal
sharing).
• User Fees and Charges: These revenues include a variety of
license and permit fees, facility and program fees, and fines.
They are rarely used as debt security for non - Enterprise Fund
capital projects, but could be a source of direct funding of a
small capital improvement.
• Enterprise Fund User Fees: These revenues are derived from
self - supporting business enterprises (Country Club) which
provide services in return for compensation. The enterprise
revenue used to secure debt is commonly termed "net -
revenue" consisting of gross revenues less operating costs.
• Note: A written, short-term promise to repay a specified
amount of principal and interest on a certain date, payable
from a defined source of anticipated revenue. Usually notes
mature in one year or less. Rarely used by the Village.
FY 2015 Proposed Budget Page 234 of 297
• Commercial Paper: Generally defined as short term,
unsecured promissory notes issued by organizations of
recognized credit quality, usually a bank. Rarely used by the
Village.
• Grant: Contribution or gift of cash or other asset from
another government to be used or expended for a specific
purpose, activity or facility.
• Developer Contributions: Monies paid by developers in lieu
of land dedications. These contributions are used for parks
and recreational purposes.
• Capital Improvement Plan (CIP) Funds: Periodically,
General Fund budgetary savings at fiscal year -end are
transferred to the Village's Capital Projects Fund as "CIP
Funds ". These savings roll over from year to year and are
utilized for funding the Five -Year Capital Improvement Plan
(CIP); this process reduces the impact of the CIP on the
Village's Annual General Fund Budget and millage rate.
Village Council approval is required for both the transfer and
use of CIP Funds.
• Unassigned Fund Balance: Fund balance that has not been
assigned to other funds and has not been restricted,
committed or assigned to specific purposes within the general
fund.
• Bond: An issuer's obligation to repay a principal amount on
a certain date (maturity date) with interest at a stated rate.
Bonds are distinguishable from notes in that notes mature in
a much shorter time period.
General Obligation Bonds: A bond secured by the
full faith and credit of the Village's ad valorem taxing
power. These are not used by the Village due to
the requirement for a voter referendum.
Revenue Bonds: Bonds payable from a specific
revenue source, not the full faith and credit of an
issuer's taxing power and require no electoral
approval. Pledged revenues are often generated by
the operating or project being financed.
The administrative ability to seek and utilize the best possible
source, or combination of sources, from the various alternatives for
financing Capital Improvements can maximize the Village's Capital
Improvement Plan, saving the cost of inefficiencies, which occur
from not adequately addressing capital needs. The future
development, growth and general well being of our citizens are
directly related to an affordable and realistic Capital Improvement
Plan.
THE CIP SCHEDULE AND PROJECT LISTS
The CIP includes a comprehensive listing of all projects contained in
the Five -Year CIP. Projects included in the CIP were evaluated
based on the criteria mentioned above. Application of these criteria
ensures that each project recommended for Council consideration
does indeed support the policy objectives of the Village's long -term
planning documents and identifies a basis for scheduling and
allocation of resources. The Fiscal Year 2015 -2019 CIP
recommends a total investment of $9.45 million in the Village of
North Palm Beach's capital facilities and equipment during a
five -year period.
FY 2015 Proposed Budget Page 235 of 297
The first year (2014) is the most active and important year of the CIP. The total budget request for capital improvements in FY 2015 is $4,564,634;
however, $10,000 will be funded in the General Fund Annual Budget. The remaining amount ($4,554,634) will be funded as follows: $2,100,000
will be funded with Grant Funds and $2,454,634 will be funded with CIP Funds. A brief summary of the first year of the plan (2015) is as follows:
Description
Annual
Budget
Grant Funds
CIP Funds
Air Handler Replacement
$ 84,634
Vehicle Replacement
$623,000
Community Development Printer /Plotter
$ 5,000
Police Radio Replacement
$154,000
Police CADS stem
$512,000
Boat Engine Replacement
$ 32,000
Front Load Dum sters - Comm. Accounts
$110,000
Earman River Irrigation Pump Station
$ 80,000
Energy Conservation Retrofits
$ 30,000
Asphalt Resurfacing - Alleys
$150,000
Service Alley Wall — East
$100,000
PW Site Drainage & Lot Resurfacing
$130,000
PW Vehicle Work Bay
$ 50,000
Power -lift Stretchers
$ 67,000
Hydraulic Extrication Tools
$ 72,000
Gymnasium Divider
$ 15,000
Pool Chlorination Feeder
$ 15,000
Kiddie Pool Renovation
$150,000
Pool Heater
$ 35,000
Comm. Center Parking Lot Resurfacing
$ 40,000
Capital Contingency — Emergency Purchase/Repair
$10,000
Anchorage Park
$2,100,000
Total
$10,000
$2,100,000
$2,454,634
The five year CIP is presented in the following pages along with the detailed capital project request forms for the first year of the plan (2015). These
request forms list the capital item to be undertaken or purchased, the estimated impact on the operating budget, and the method of financing the
proj ect.
FY 2015 Proposed Budget Page 236 of 297
Vill _
6,894,484
72.94%
Village of North Palm Beach
Five Year CIP Summary
Fiscal Year 2015 - 2019
Funding Source 2,10000 rant
Machinery 8
Equipment
1,219,634
12.90%
Construction
Renoval
3,545,000
37.50%
Playground & Outside Cateeory fmmniitarllarrhAnra
Lease
158,000
4.85%
Pul
3
Parks
2,
26.75%
Total 5 Year CIP
$9,452,484
Department Community
Department
62,634
0.66%
Club
00
YO
FY 2015 Proposed Budget Page 237 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan Summary
FY 2015 -2019
FY 2015 Proposed Budget Page 238 of 297
Cost by CIP Year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Category / Department
Automotive:
Commurfity Development
20,000
$ 20,000
Country Club
458,000
26,000
$ 484,000
Police and Fire
168,500
485,000
944,000
171,000
238,000
$ 2,006,500
Public Works
454,500
413,500
302,125
320,225
85,000
$ 1,575,350
Parks & Recreation
$
Subtotal Automotive:
623,000
1,376,500
1,246,125
517
323,000
$ 4,085,850
Machinery & Equipment:
Country Club
$
Corinininity Development
5,000
$ 5,000
Library
62,634
$ 62,634
Police and Fire
325,000
22,000
117,000
$ 464,000
Public Works
190,000
206,000
108,000
35,000
$ 539,000
Parks & Recreation
87,000
47,000
15,000
$ 149,000
Subtotal Machinery & Equipment
669,634
275,000
108,000
50,000
117,000
$ 1,219,634
Construction & Major Renovation:
Corinininity Development
$
Library
$
Public Works
460,000
345,000
150,000
150,000
$ 1,105,000
Parks & Recreation
2,290,000
$ 2,290,000
Country Club
$
Police and Fire
150,000
$ 150,000
Subtotal Construction & Major Renovation
2,750,000
495,000
150,000
150,000
-
$ 3,545,000
Computer Hardware & Software:
Police and Fire
512,000
$ 512,000
Subtotal Computer Hardware & Software
512,000
-
-
-
-
$ 512,000
Playground & Outside Equipment:
Parks & Recreation
45,000
45,000
$ 90,000
Subtotal Playground& Outside Equipment
-
45,000
-
-
45,000
$ 90,000
Estimated Total Cost
$ 4,554,634
$ 2,191,500
$ 1,504,125
$ 717,225
$ 485,000
$ 9,452,484
Funding Source
FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Village
2,454,634
1,733,500
1,504,125
717,225
485,000
$ 6,894,484
Capital Projects Fund (CIP)
$
Grant
2,100,000
$ 2,100,000
Lease
458,000
$ 458,000
Developer Contribution
$
Estimated Total Funding
$ 4,554,634
$ 2,191,500
$ 1,504,125
$ 717,225
$ 485,000
$ 9,452,484
FY 2015 Proposed Budget Page 238 of 297
FY 2015 Proposed Budget Page 239 of 297
The Village of North Pahn Beach
Fiscal Year 2014 -2015 Budget
General Fund Capital Outlay (Funding Source: CIP Funds)
Department
Amount
Community Development
Printer/Plotter
5,000
5,000
Library
Air Handler replacement (6)
62,634
62,634
Police
Vehicle Replacement - Unmarked Taurus
33,000
Vehicle Replacement - Marked Black/White Explorer
36,500
Vehicle Replacement - Marked Black/White Taurus
35,500
Vehicle Replacement - Marked K -9 Black/White Explorer
36,500
Police Radio Replacement
154,000
CAD System (S480k Software / S32k Hardware + License)
512,000
Replacement Boat Engines
32,000
839,500
Fire Rescue
Power -lift Stretchers
67,000
Hydraulic Extrication Tools
72,000
Vehicle Replacement - Pickup Truck
27,000
166,000
Public Works
Machinery & Equipment:
Front Load Sanitation Collection Truck
255,000
Front Load Dumpsters - Commercial Accounts
110,000
Grapple Collection Truck
130,000
Carolina Skiff J -Series Platform Boat
12,500
Ford F -450 Crew Cab Truck
57,000 564,500
Improvements:
Farman River Irrigation Pump Station
80,000
Energy Conservation Retrofits
30,000
Asphalt Resurfacing - Alleys
150,000
Service Alley Wall - East
100,000
PW Site Drainage & Lot Resurfacing
130,000
Public Works Vehicle Work Bay
50,000 540,000
1,104,500
Parks & Recreation
Gymnasium Divider
15,000
Pool Chlorination Feeder
15,000
Kiddie Pool Renovation
150,000
Air Handler replacement (2)
22,000
Pool Heater
35,000
Community Center Parking Lot Resurfacing
40,000
Anchorage Park Phase 2 ( *)
2,100,000
2,377,000
* Subject to approval ofgrantfzmding
Total Fiscal Year 2014 -2015 Capital Outlay (IncludesAnchorage ParkPhase 2 Project)
$ 4,554,634
Total Fiscal Year 2014 -2015 Capital Outlay (Doesn't include Anchorage Park Phase 2 Project)
$ 2,454,634
Prioritv
1
1
1
1
1
1
2
3
4
1
2
3
1
2
3
3
4
1
2
3
4
5
5
1
2
3
4
5
6
7
FY 2015 Proposed Budget Page 240 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan
FY 2015 -2019
Fund: General Fund Department: Community Development Division: All Divisions
Cost by CIP Year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Description
Current Inventory
Estimated Life
Automotive:
$
S10 Pickup
2009(l)
7 Years / 100k miles
20,000
S 20,000
F150 Pickup
2013 (1); 2014 (4)
7 Years/ 100k miles
S -
Suhtotal Automotive
20,000
S 20,000
Computer Hardware & Software:
$ -
New Software
2011
S
Suhtotal Computer Hardware & Software
-
$
Machinery & Equipment:
$
Printer Plotter
10 Years
5,000
$ 5,000
Subtotal Machinery & Equipment
5,000
$ 5,000
Construction & Major Renovation:
$
Building Department Renovation
2014
5 Years
$
Suhtotal Construction & Renovation
-
$
Estimated Total Cost
$ 5,000
$ 20,000
$
$
$
$ 25,000
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Village
5,000
20,000
$ 25,000
Grant
$ -
Other
$ -
Estimated Total Funding
$
$ 20,000
$
$
$
$ 25,000
Annual Operating Cost Increases Created by Project:
Description of Operating Impact: No operating Impact; Printer Plotter
FY 2015 Proposed Budget Page 241 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Community Development
Project Title:
Plotter Printer
Division: Building Department
Description/Detail:
Purchase Plotter Printer
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
I
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
X
Improve procedures, records, etc.
Purchase Price
5,000.00 $ 5,000.00
Increased safety
PIns: Installation or other costs
$ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 5,000.00 $ 5,000.00
Replaced item(s):
Item
Disposition Method
$ 5,000.00 Village
Lease
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Capability to print large 2406 scanned plans
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 242 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan
FY 2015 -2019
Fund: General Fund Department: Library Division: N/A
Cost by CIP Year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Description
Current Inventory
Estimated Life
Construction & Major Renovation:
x -
Roof re lacement
2014 ( *)
30 -39 years
x
Replace lobby windows
2014 ( *)
40 years
$
x
Suhtotal Construction & Major Renovation
$
Machinery & Equipment:
Replace A/C Handlers
l0 -15 years
62,634
$ 62,634
uhtotal Machinery & Equipment
62,634
$ 62,634
Estimated Total Cost
62,634
$ 62,634
Funding Source
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Village
62,634
$ 62,634
Grant
$
Other
$
Estimated Total Funding
62,634
$ 62,6-
( *) Projects expected to he completed prior to Fiscal Year ending 09130114.
Annual Operating Cost Increases Created by Project:
Description of Operating Impact: No operating Impact
FY 2015 Proposed Budget Page 243 of 297
it -a
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
General Fund Department:
ct Title: A/C Air Handlers Division:
iotion/Detail: Replace six (6) A/C Air Handlers
Machinery & Equipment ( 466490)
Furniture & Fixtures ( 966430)
Computer Hardware & Software ( 966415)
Automotive ( 966410)
of Expenditure (Check Appropriate):
Scheduled replacement
Present equipment obsolete
x Replace worn-out equipment
Improve procedures, records, etc.
Increased safety
Construction/Major Improvement
Other (Please specify)
Replaced item(s):
Item Disposition Method
Older Air Handlers discard
Im pact: none
of units requested:
;base Price
: Installation or other costs
Trade -in or other discount
Purchase Cost
mated Useful Life in Years:
ding Source (List Amount):
62,634.00 Village
Grant
Debt Service
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection # Capital Cateeory Capitalization Threshold
Selection #:
Capital Category:
Capitalization Threshold:
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
Comment:
Audio, Visual, Comm. Systems ( 466440)
Playground & Outside Equipment ( 466422)
Office Equipment ( 966420)
Construction & Major Renovation ( 966210)
6
Per Unit Total
10,439.00 $ 62,634.00
$ 10,439.00 $ 62,634.00
10 to 15 years
5 vear CIP?
Lease
Developer Fees
Other
FY 2015 Proposed Budget Page 244 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan
FY 2015 -2019
Fund: General Fund Department: Police and Fire Division: N/A
Cost by CIP Year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year #1 (Year #2 (Year #3 (Year #4 (Year #5
Description
Current Inventory
Estimated Life
Automotive:
Patrol/ Vehicles
2014 (2); 2012 (2); 2011 (1);
2010 (3); 2008 (1); 2007 (5);
2005 3
7 years or 100,000 miles
72,000
136,000
140,000
102,000
136,000
$ 586,000
Patrol Boat
1999 (1)
15 years
$
Undercover Vehicles
2014 (1); 2012 (2); 2008 (2);
2008 (1); 2007 (1); 2004 1
7 years or 100,000 miles
33,000
99,000
70,000
34,000
102,000
$ 338,000
Marine Unit Track
2002(l)
7 years or 100,000 miles
34,000
$ 34,000
K -9 Vehicles
2008(l)
7 years or 100,000 miles
36,500
$ 36,500
Crime Scene Vehicle
1996(l)
10 years
$
Fire Engine
2003 2
20 years
$
Yukon
2004(l)
10 years
35,000
$ 35,000
Tahoe
2013 1
10 years
$
Support Track
1987(l)
30 years
100,000
$ 100,000
5 -10 Pick-Up Track
2002(l)
13 years
27,000
$ 27,000
Quintuplet Fire Apparatus
1997(1)
20 years
600,000
$ 600,000
Ambulance
2003 1 2010 1
6 years
250,000
$ 250,000
SubtotalAutomotive:
168,500
485,000
944,000
171,000
238,000
$ 2,006,500
Computer Hardware & Software:
CADS stem
512,000
$ 512,000
Subtotal Machinery &Equipment
512,000
$ 512,000
Construction & Major Renovation:
Replace stonework & windows
150,000
$ 150,000
Subtotal Construction &Major Renovation:
150,000
$ 150,000
achinery & Equipment:
Breathing Air Compressor
1999 (1)
20 years
50,000
$ 50,000
Cardiac Monitor /Defibrillator
2002 1 2004 2 2009 2
5 years
67,000
$ 67,000
Self- contained Breathing Apparatas
2013 27
12 years
$
Hydraulic Extriction Tools
2003 2
12 years
72,000
$ 72,000
Power Stretchers
2008 (2)
7 years
67,000
$ 67,000
TM-I Imaging Camera
2014 (2)
12 years
$
Automatic External Defibrillators (AED)
2009 11
7 years
22,000
$ 22,000
60 Ton A/C Chiller
2012
10 -12 years
$
Re lace garage doors
2014 (6)
15 years
$
Replacement Boat Engines
2009(l)
3 years
32,000
$ 32,000
Radio System
2008
10 years
154,000
S 154,000
Subtotal Machinery &Equipment
325,000
22,000
117,000
464,000
Estimated Total Cost
$ 1,005,500
$ 657,000
1 $ 944,000
$ 171,000
$ 355,000
$ 3,132,500
Funding Source
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Village
1,005,500
657,000
944,000
171,000
355,000
$ 3,132,500
Grant
$
Other
$
Estimated Total Funding
$ 1,005,500
$ 657,000
$ 944,000
$ 171,000
$ 355,000
$ 3,132,500
Annual Operating Cost Increases Created by Project: $
Description of Operating Impact: No operating Impact
FY 2015 Proposed Budget Page 245 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police Department
Project Title:
Vehicle Replacement
Division: N/A
Description/Detail:
Replace 1 Unmarked Police Vehicle
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
33,000.00 $ 33,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 33,000.00 $ 33,000.00
7
Replaced item(s):
Item
Disposition Method
$ 33,000.00 Village
Lease
2008 Ford Crown Victoria
Auction
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 246 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police Department
Project Title:
Vehicle Replacement
Division: N/A
Description/Detail:
Replace 1 Marked Police Vehicle
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
36,500.00 $ 36,500.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 36,500.00 $ 36,500.00
7
Replaced item(s):
Item
Disposition Method
$ 36,500.00 Village
Lease
2010 Ford Crown Victoria
Auction
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 247 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police Department
Project Title:
Vehicle Replacement
Division: N/A
Description/Detail:
Replace 1 Marked Police Vehicle
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
35,500.00 $ 35,500.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 35,500.00 $ 35,500.00
7
Replaced item(s):
Item
Disposition Method
$ 35,500.00 Village
Lease
2008 Ford Crown Victoria
Auction
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 248 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police Department
Project Title:
Vehicle Replacement
Division: N/A
Description/Detail:
Replace 1 Marked Police Vehicle
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
36,500.00 $ 36,500.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 36,500.00 $ 36,500.00
7
Replaced item(s):
Item
Disposition Method
$ 36,500.00 Village
Lease
2008 Ford Crown Victoria
Auction
Grant
Developer Fees
K -9
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 249 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police Department
Project Title:
Boat Engine Replacement
Division: N/A
Description/Detail:
Replace 1 Boat Engine
Capital Account (Check A propriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
32,000.00 $ 32,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 32,000.00 $ 32,000.00
Replaced item(s):
Item
Disposition Method
$ 32,000.00 Village
Lease
09 Contender Boat Engine
Auction
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 250 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police
Project Title:
CAD System Replacement
Division: N/A
Description/Detail:
We have reached our end of life cycle for our police radios stem, CAD system (Computer Aided Dispatch) and hardware in support of
CADS, Records and Dispatch.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
X
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
X
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
512,000.00 $ 512,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 512,000.00 $ 512,000.00
6 -10 years
Replaced item(s):
Item
Disposition Method
$ 512,000.00 Village
Lease
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 251 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Police
Project Title:
Police Radio Replacement
Division: N/A
Description/Detail:
We have reached our end of life cycle for our police radios stem, CAD system (Computer Aided Dispatch) and hardware in support of
CADS, Records and Dispatch.
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
X
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
154,000.00 $ 154,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 154,000.00 $ 154,000.00
6 years
Replaced item(s):
Item
Disposition Method
$ 154,000.00 Village
Lease
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Other Comment:
Current Vendor will end support of the current radios in 2015
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 252 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Fire Rescue
Project Title:
Power -lift stretchers
Division: N/A
Description/Detail:
Replacement of two 2 seven year old power-lift stretchers that have met their useful service life,
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
2
X
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
33,500.00 $ 67,000.00
X
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 33,500.00 $ 67,000.00
7 years
Replaced item(s):
Item
Disposition Method
$ 67 000.00 Village
Lease
Power -lift stretchers
junk/obsolete
Grant
Developer Fees
Debt Service
Other
Operating Impact:
No additional budget impact. Replaces items one for one.
Other Comment:
Current units are first generation technology that are obsolete.
New units provide enhanced operating capabilities and reduce
the lifting effort of the ambulance crew, which reduces the risk
of employee injury.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP7
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 253 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Fire Rescue
Project Title:
Hydraulic Extrication Equipment
Division: N/A
Description /Detail:
Replacement of two 2 sets of h draulic extrication equipment that have reached their useful service life.
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
2
X
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
36,000.00 $ 72,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 36,000.00 $ 72,000.00
12 years
Replaced item(s):
Item
Disposition Method
$ 72 000.00 Village
Lease
Hydr. Extrication Equip.
Auction /Sell outright
Grant
Developer Fees
Debt Service
Other
Operating Impact:
No additional budget impact. Replaces items one for one.
Other Comment:
May result in reduced maintenance cost due to new
warranty.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category Capitalization Threshold Capital Outlay?
5 year CIP7
4
Machinery & Equipment 5,000 Yes
Include in CIP
Selection #:
Capital Category: Capitalization Threshold:
1
Land Improvement 25,000
2
Building 50,000
3
Building Improvement 50,000
4
Machinery & Equipment 5,000
5
Vehicle 5,000
6
Infrastructure 250,000
FY 2015 Proposed Budget Page 254 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Fire Rescue
Project Title:
Vehicle Replacement
Division: N/A
Description/Detail:
Replacement of one 1 2002 Chevrolet S -10 pickup truck.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
27,000.00 $ 27,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 27,000.00 $ 27,000.00
7 years / 100,000 miles
Replaced item(s):
Item
Disposition Method
$ 27 000.00 Village
Lease
2002 S -10 pickup
Auction
Grant
Developer Fees
Debt Service
Other
Operating Impact:
No additional budget impact.
Other Comment:
Replace 2002 Chevrolet S -10 pickup truck with a full -size
pickup truck.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP7
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 255 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan
FY 2015 -2019
Fund: General Fund Department Public Works Division: All Divisions
Cost by CIP Year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Bud etYear ear #1 ear #2 ear #3 ear #4 ear #5
Description
Current Inventory
Estimated Life
[omotive:
Utilty Service Bucket Truck
2000(l)
12 years
98,500
$ 98,500
Sanitation Collection Truck
2001 (1); 2002 (1); 2004 (1);
2006 1;2007 2;2009 1
10 ears
255,000
257,500
260,125
262,725
$ 1,035,350
Grapple Collection Truck
2003(l)
7 years
130,000
$ 130,000
Street/Puking Area Sweeper
10 Years
57,500
$ 57,500
D-T, Truck
2006(l)
12 years
85,000
$ 85,000
F450 Crew Cab Truck
2000(l)
12 years
57,000
$ 57,000
Colorado Picku p Truck
2006(l)
10 years,
16,000
$ 16,000
Dodge 2500 RAM Service Body
2006(l)
10 ears
26,000
$ 26,000
Small Dum p Truck
2000(l)
12 years
31,500
$ 31,500
Dodge 2500 R -Picku
2007(l)
10 ears
26,000
$ 26,000
F250 Utility Service Body
2014(l)
10 years
$
E350 Service Van
2014(l)
10 years
$
Dodge 2500 RAM
2010(l)
10 years
$
Ford Fl50 Picku p Truck
2014(l)
10 years
$
F350 Truck Pick Truck
1995(l)
12 years
$
Ram 3500 Flatbed
20071
15 years
$
F350 Truck Pick Truck
1995(l)
12 years
$
Ford F150 Picku p Truck
2014(l)
10 ears
$
Carolina SkiffJ Series WorkPlatfom Boat
15 years
12,500
$ 12,500
Subtotal Automotive:
454,500
413,500
302,125
320,225
85,000
$ 1,575,350
Construction & Major Renovation:
Energy Conservation Retrofits
20 years
30,000
70,000
$ 100,000
PW Puking Lot Drainage & Resurfacing
15 years
130,000
$ 130,000
Asphalt Resurfacing-Streets
2011
10 years
150,000
150,000
150,000
$ 450,000
Asphalt Resurfacing-Alleys Resurfincing-Alleys
2013
10 ears
150,000
$ 150,000
Service Alley Wall
20 years
100,000
100,000
$ 200,000
Village Wide Sidewalks
2013
25,000
$ 25,000
Public Works Vehicle Work Bay
15 years
50,000
$ 50,000
Subtotal Construction &Major RenwaHon
460,000
345,000
150,000
150,000
$ 1,105,000
Machinery & Equipment:
Curotto Can Automated Collector
6 Years
35,000
35,000
35,000
$ 105,000
Sanitation Service Vehicle
8 years
36,000
18,000
$ 54,000
Front Load Dum sters
7 years
110,000
135,000
$ 245,000
John Deere Combination
1999(l)
15 years
55,000
$ 55,000
Bobcat 5570
2013(l)
10 ears
$
New Holland Tractor
2006(l)
15 years
$
E- River ffii ation P-T, Station
15 years
80,000
s 80,000
Subtotal Machinery & Equipment
190,000
206,000
108,000
35,000
$ 539,000
Estimated Total Cost
$ 1,104,500
$ 964,500
$ 560,125
$ 505,225
$ 85,000
$ 3,219,350
Funding Source
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year #1) (Year #2) (Year #3) (Year #4) (Year #5)
Villa General Fund
1,104,500
964,500
560,125
505,225
85,000
$ 3,219,350
Grant
$
Other
$
Estimated Total Funding
$ 1,104,500
$ 964,500
$ 560,125
$ 505,225
$ 85,000
s 3,219,350
Description of Operating Impact No operating Impact
FY 2015 Proposed Budget Page 256 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Front Load Sanitation Collection Truck
Division: Sanitation
Description/Detail:
Front -Load Sanitation Collection Truck
conversion from Rear -Load Packer Trucks.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
•
Scheduled replacement
Number of units requested:
1
X
Present equipment obsolete
•
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
255,000.00 $ 255,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
- $ -
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 255,000.00 $ 255,000.00
10 Years
Replaced item(s):
Item
Disposition Method
$ 255,000.00 Village
Lease
Grant
Developer Fees
Vehicle # 66
Surplus Auction
Debt Service
Other
Operating Impact:
Other Comment:
The Sanitation Division fleet is proposed to be converted from Rear -Load Packer Collection vehicles to
Reduction in annual maintenance
expense associated with this
vehicle.
Front -Load Collection vehicles.
Front -Load Collection vehicles provide greater flexibility and insure
our capability to continue
the Village's unique sanitation collection service. This conversion will reduce
annual operating expenses
and allow for the development of new revenue sources. Once the conversion
is complete, we anticipate
a reduction in fleet size by one (1) collection vehicle and reduction in staff of
20% or four (4) FTE.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 257 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Front Load Dumpsters (200 Commercial)
Division: Sanitation
Description/Detail:
Front -load dum ster route conversion.
Commercial customer dumpsters.
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
110,000.00 $ 110,000.00
X
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 110,000.00 $ 110,000.00
7 Years
Replaced item(s):
Item
Disposition Method
$ 110,000.00 Village
Lease
Grant
Developer Fees
N/A
N/A
Debt Service
Other
Operating Impact:
Other Comment:
In conjunction with the Sanitation Division fleet conversion, it will be necessary to complete a full route
conversion from rear -load
to front -load dumpsters. The route conversion would eliminate the costly
expense to businesses
and multi - family buildings in purchasing and maintaining dumpsters.
Additionally, the conversion
will reduce Public Works annual operating expenses and allow for the
development of a new
revenue source. Salvage value for replaced dumpsters is anticipated to be
$20,000.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 258 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Carolina Skiff J Series Platform Boat Division: Streets & Grounds
Description/Detail:
Public Works proposes the purchase
of a 2014 Carolina Skiff J Series work boat.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415) Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested: 1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
X
Improve procedures, records, etc.
Purchase Price 12,500.00 $ 12,500.00
Increased safety
PIns: Installation or other costs - $ -
Construction/Major Improvement
Less: Trade -in or other discount - $ -
X
Other (Please specify)
Net Purchase Cost $ 12,500.00 $ 12,500.00
Estimated Useful Life in Years: 15 -20 Years
Funding Source (List Amount):
Replaced item(s):
Item
Disposition Method
$ 12,500.00 Village Lease
Grant Developer Fees
N/A
N/A
Debt Service Other
Operating Impact:
Other Comment:
Public Works proposes the purchase of a 2014 Carolina Skiff J Series work boat. The boat
would allow water level access to outfalls for the purpose of inspection and maintenance. The
Reduction in annual operating expense for contract services.
boat is designed for confined area swallow water work. The proposal includes boat, 30HP
motor, and trailer. The boat is equipped for working and storage of equipment and gear. It
does not include rod holders, bait wells, coolers, or a fish box.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay? 5 year CIP?
5
Vehicle
5,000 Yes Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 259 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Grapple Collection Truck
Division: Sanitation
Description/Detail:
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
130,000.00 $ 130,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
- $ -
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 130,000.00 $ 130,000.00
Replaced item(s):
Item
Disposition Method
$ 130,000.00 Village
Lease
Grant
Developer Fees
N/A
N/A
Debt Service
Other
Operating Impact:
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
5
Vehicle
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 260 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Vehicle Replacement
Division: Streets & Grounds
Description/Detail:
Replacement of 2000 Ford F450 Crew Cab.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
X
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
1
X
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
57,000.00 $ 57,000.00
Increased safety
Plus: Installation or other costs - $ -
Construction/Major Improvement
Less: Trade -in or other discount $
Other (Please specify)
Net Purchase Cost $ 57,000.00 $ 57,000.00
Estimated Useful Life in Years: 12 Years
Funding Source (List Amount):
Replaced item(s):
Item
Disposition Method
$ 57,000.00
Village Lease
Grant Developer Fees
Vehicle PW # 34
Surplus Auction
Debt Service Other
Operating Impact:
Other Comment:
Public Works Streets & Grounds Division vehicle 434 is a 2000 Ford F450 Crew Cab Flatbed.
Reduction in annual maintenance
expense associated with this
equipment.
Additionally, due to changes in operational means and methods, this vehicle is operationally obsolete.
The proposed replacement vehicle is a 2014 Ford F450 Crew Cab High -Wall Dump -Bed. The
replacement vehicle has a greater towing capacity, high -wall aluminum bed, and the ability to dump the
bed. These options provide greater capability and reduce staff time dedicated to tasks. We anticipate
recovering $7,000 with the surplus sell of the existing vehicle.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold
Capital Outlay? 5 year CIP?
5
Vehicle
5,000
Yes Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 261 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Farman River Irrigation Pump Station
Division: Streets & Grounds
Description/Detail:
Public Works proposes the construction of a dual pump station in place of the existing.
Ca ital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
X
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
80,000.00 $ 80,000.00
Increased safety
Plus: Installation or other costs
- $ -
X
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 80,000.00 $ 80,000.00
15 Years
Replaced item(s):
Item
Disposition Method
$ 80,000.00 Village
Lease
Grant
Developer Fees
N/A
N/A
Debt Service
Other
Operating Impact:
Other Comment:
Reduction in annual operating expense and IQ irrigation water.
The Village relies on a single (1) 40HP pump and motor to draw water from the C -17 canal
( Earman River) for irrigation. The irrigation locations include Osborne Park, Lakeside Park,
Public Safety, Village
Hall, Library, Veteran's Park, U.S. 1 medians, and Country Club golf
course. Public Works
proposes the construction of a dual pump station in place of the
existing.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 262 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Energy Conservation Retrofits
Division: Facility Services
Description/Detail:
Energy conserving retrofits to Village facilities.
Village Hall & Street Lights
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
X Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
30,000.00 $ 30,000.00
Increased safety
Plus: Installation or other costs - $ -
X
Construction/Major Improvement
Less: Trade -in or other discount $
Other (Please specify)
Net Purchase Cost $ 30,000.00 $ 30,000.00
Estimated Useful Life in Years: 20 Years
Funding Source (List Amount):
Replaced item(s):
Item
Disposition Method
$ 30,000.00
Village Lease
Grant Developer Fees
N/A
N/A
Debt Service Other
Operating Impact:
Other Comment:
The Village's annual operating expense for electricity is approximately $400,000. Following
Reduction it annual electricity
charges and maintenance expense.
the completion of an energy audit, Public Works seeks to reduce our overall operating
Phase 1 - Vil
Village Hall
&Street Lights
expense for electricity by a minimum of 20% or $80,000 annually. This will be accomplished
through the installation of energy conserving components such as LED lighting, occupancy
sensors, and time -of -use control clocks.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold
Capital Outlay? 5 year CIP?
3
Building Improvement
50,000
No Do not include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 263 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Asphalt Resurfacing - Alley
Division: Streets & Grounds
Description/Detail:
Public Works proposes the milling and resurfacing of the select portion of the west U.S. 1 corridor alley.
Capital Account (Check Appropriate):
Machinery & Equipment ( 466490)
Audio, Visual, Comm. Systems ( 466440)
Furniture & Fixtures ( 466430)
Playground & Outside Equipment ( 466422)
Computer Hardware & Software ( 466415)
Office Equipment ( 466420)
Automotive ( 466410)
X
Construction & Major Renovation ( 466210)
Other Capital ( 466000)
Developer Fees Capital Purchase ( 466005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn-out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
150,000.00 $ 150,000.00
Increased safety
Plus: Installation or other costs
- $
Construction/Major Improvement
Less: Trade -in or other discount
- $
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source( istAmount):
$ 150,000.00 $ 150,000.00
10 -15 Years
Replaced item(s):
Item
Disposition Method
$ 150,000.00 Village
Lease
Grant
Developer Fees
N
N/A
Debt Service
Other
Operating Impact:
Other Comment:
Public Works proposes
the milling and resurfacing of the select portion of the west U. S. 1 corridor
alley. The condition of the alley in select locations has deteriorated and warrants maintenance. The
Reduction in annual
maintenance expense.
road base material does
not appear to have been compromised at this time and the most appropriate
repair method is by removing
(milling) the top 1 ° of the existing pavement and replacing it with a
new layer of asphalt. This repair method should extend the select alley sections useful service life
y a minimum of 10 years.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
1
Land Improvement
25,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 264 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Service Alley Wall Replacement- East Division: Streets & Grounds
Description/Detail:
Public Works proposes the gradual removal and replacement of the existing privacy wall for the east U.S. 1 corridor alley.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415) Office Equipment ( #66420)
Automotive ( #66410)
X Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested: 1
Present equipment obsolete
X
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price 100,000.00 $ 100,000.00
Increased safety
Plus: Installation or other costs - $ -
Construction/Major Improvement
Less: Trade -in or other discount - $ -
Other (Please specify)
Net Purchase Cost $ 100,000.00 $ 100,000.00
Estimated Useful Life in Years: 15 -20 Years
Funding Source (List Amount):
Replaced item(s):
Item
Disposition Method
$ 100,000.00 Village Lease
Grant Developer Fees
N/A
N/A
Debt Service Other
Operating Impact:
Other Comment:
Public Works proposes the gradual removal and replacement of the existing privacy wall for
the east U.S. 1 corridor alley. We have a limited supply of replacement panels and the original
Reduction in annual maintenance
expense.
manufacturer no longer makes the panels. The west alley wall has been replaced with a
concrete block wall, which is more durable and requires less maintenance. Public Works
proposes to replace the existing east alley post and panel wall with a concrete block wall over
the next two 2 fiscal years.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay? 5 year CIP?
1
Land Improvement
25,000 Yes Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 265 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
PW Site Drainage & Lot Resurfacing
Division: Facility Services
Description/Detail:
Site drainage improvement to elinate flooding events. Reconfir ure and resurface site layout.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
X
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
130,000.00 $ 130,000.00
Increased safety
Plus: Installation or other costs
- $ -
X
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 130,000.00 $ 130,000.00
20 Years
Replaced item(s):
Item
Disposition Method
$ 130,000.00 Village
Lease
Grant
Developer Fees
N/A
N/A
Debt Service
Other
Operating Impact:
Other Comment:
N/A
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
3
Building Improvement
50,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 266 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Public Works
Project Title:
Public Works Vehicle Work Bay
Division: Facility Services
Description/Detail:
Construct a vehicle maintenance work bay.
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
X
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
50,000.00 $ 50,000.00
Increased safety
Plus: Installation or other costs
- $ -
X
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 50,000.00 $ 50,000.00
20 Years
Replaced item(s):
Item
Disposition Method
$ 50,000.00 Village
Lease
Grant
Developer Fees
N/A
N/A
Debt Service
Other
Operating Impact:
Other Comment:
Meet vehicle maintenance
needs for Sanitation Division equipment
changes.
In conjunction with the
Sanitation Division fleet conversion, it will be necessary to construct a
vehicle work bay at the
Public Works complex. The existing facility is not equipped to
maintain front -load collection vehicles and requires a retrofit. This work bay will also be
utilized in the repair and maintenance of Public Safety Fire Rescue vehicles.
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
3
Building Improvement
50,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 267 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan
FY 2015 -2019
Fund: Cencral Ruud Department: Parks & Recreation Division: All Divisions
Cost by Cl P Year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Description
Current Inventory
Estimated Life
Automotive:
Sport Utility Vehicle / Blazer
2011(l)
10 years
$
Mini -Bus
2000 (1) 2013 (1)
12 years
$
Pick Up truck
2014(l)
9 yem
$
Subtotal Automotive:
-
-
-
-
$ -
Machinery & Equipment-
Package A/C Units
2001 (2) 2002 (4)
12 years
22,000
$ 22,000
Lightning Detection System
2008, 2011, 2014
10 years
15,000
$ 15,000
Pool Heaters
2007 (2)
7 yeus
35,000
35,000
$ 70,000
Chlorination feeder
1997
10 years
15,000
$ 15,000
Gym Divider
1982
20 years
15,000
$ 15,000
Co=mity Center Lighting Conversion
1989
15 years
12,000
$ 12,000
Indoor bleachers
2014
25 years
$
P=p & well
2012
20 years
$
Relight Osborne Park
2013
20 years
$
Subtotal Machinery & Equipment
87,000
47,000
-
15,000
-
$ 149,000
Playground & Outside Equipment-
PlaygromdEquipmmt
Various Parks
12 years
45,000
45,000
$ 90,000
Subtotal Playground & Outside Equipment
-
45,000
-
-
45,000
$ 90,000
Construction & Major Renovation:
Kiddie Pool Renovation
20 years
150,000
$ 150,000
Pool Resurfacing
2011
15 years
$
P=p Room Renovation
2011
25 years
$
Memorial Park
2013
20 years
$
Co=mity Center Puking Lot Resurfacing
20 years
40,000
$ 40,000
Anchorage Park Renovation - Phase 2
( *) See note
20 years
2,100,000
$ 2,100,000
Subtotal Construction & Major Renovation
2,290,000
-
-
-
-
$ 2,290,000
Furniture & Fixtures:
Subtotal Furniture & Fixtures
-
-
-
-
-
$ -
Estimated Total Cost
$ 2,377,000
$ 92,000
$
$ 15,000
$ 45,000
$ 2,529,000
Funding Source
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) 1 (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Village
277,000
92,000
15,000
45,000
$ 429,000
Grant
2,100,000
$ 2,100,000
Developer Contribution
$
Other
Estimated Total Funding
$ 2,377,000
$ 92,000
$
$ 15,000
$ 45,000
$ 2,529,000
( *) The Village will appropriate any grant matching requirements upon notification of grant approval
Description of Operating Impact: No operating Impact
FY 2015 Proposed Budget Page 268 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Community Center gymnasium divider
Division: Recreation
Description/Detail:
Replacement of the existing main court divider at the Community Center gymnasium
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
I
Present equipment obsolete
X
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
15,000.00 $ 15,000.00
X
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 15,000.00 $ 15,000.00
20 years
Replaced item(s):
Item
Disposition Method
$ 15,000.00 Village
Lease
Gym divider
Retire & dispose
Grant
Developer Fees
Debt Service
Other
Operating Impact:
scheduled replacement
Other Comment:
divides the gym in half to allow two events to happen at the
same time
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 269 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Chlorination Feeder
Division: Pool
Description/Detail:
Replacement of existing feeder
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
I
Present equipment obsolete
X
Replace worn -out equipment
Per Unit Total
X
Improve procedures, records, etc.
Purchase Price
15,000.00 $ 15,000.00
X
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 15,000.00 $ 15,000.00
7 years
Replaced item(s):
Item
Disposition Method
$ 15,000.00 Village
Lease
Chlorination Feeder
Retire & dispose
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Needed to safely and correctly monitor the daily chemicals
Other Comment:
at the pool
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 270 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Kiddie Pool Renovation
Division: Pool
Description/Detail:
Renovation of kiddie pool to include its own filtrations stem and water features
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
X
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
X
Present equipment obsolete
X
Replace worn -out equipment
Per Unit Total
X
Improve procedures, records, etc.
Purchase Price
150,000.00 $ 150,000.00
X
Increased safety
Plus: Installation or other costs
- $ -
X
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 150,000.00 $ 150,000.00
20 years
Replaced item(s):
Item
Disposition Method
$ 150,000.00 Village
Lease
Existing kiddie pool
Retire & dispose
Grant
Developer Fees
Debt Service
Other
Operating Impact:
scheduled replacement
Other Comment:
Replace out of compliance kiddie pool with new renovation which
includes filtration system and water features
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
1
Land Improvement
25,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 271 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Air Condition units
Division: Recreation
Description/Detail:
Replacement of two existing air condition units at the Community Center gymnasium
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
2
Present equipment obsolete
X
Replace worn -out equipment
Per Unit Total
X
Improve procedures, records, etc.
Purchase Price
11,000.00 $ 22,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 11,000.00 $ 22,000.00
12 years
Replaced item(s):
Item
Disposition Method
$ 22,000.00 Village
Lease
Air Condition units
Retire & dispose
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Normal replacement
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 272 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Pool Heater
Division: Pool
Description/Detail:
Replacement of existing pool heater
Capital Account (Check Appropriate):
X
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
X
Replace worn -out equipment
Per Unit Total
X
Improve procedures, records, etc.
Purchase Price
35,000.00 $ 35,000.00
Increased safety
Plus: Installation or other costs
- $ -
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 35,000.00 $ 35,000.00
7 years
Replaced item(s):
Item
Disposition Method
$ 35,000.00 Village
Lease
MSCPN 1261 Heater
Retire & dispose
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Increase pool accessibility during the winter months
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
4
Machinery & Equipment
5,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 273 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Community Center Parking Lot Resurfacing
Division: Recreation
Description/Detail:
Resurfacing of the north and south parking lots at the Community Center
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
X
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
X
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
40,000.00 $ 40,000.00
X
Increased safety
Plus: Installation or other costs
- $ -
X
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 40,000.00 $ 40,000.00
20 years
Replaced item(s):
Item
Disposition Method
$ 40,000.00 Village
Lease
Lot surface
resurface
Grant
Developer Fees
Debt Service
Other
Operating Impact:
Normal resurfacing
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
1
Land Improvement
25,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 274 of 297
Village of North Palm Beach
Capital Request Form
FY 2014 -2015
Fund:
General Fund
Department: Parks & Recreation
Project Title:
Anchorage Park Phase 2
Division: Recreation
Description/Detail:
Continue with the renovation of Anchorage Park
Capital Account (Check Appropriate):
Machinery & Equipment ( #66490)
Audio, Visual, Comm. Systems ( #66440)
Furniture & Fixtures ( #66430)
Playground & Outside Equipment ( #66422)
Computer Hardware & Software ( #66415)
Office Equipment ( #66420)
Automotive ( #66410)
X
Construction & Major Renovation ( #66210)
Other Capital ( #66000)
Developer Fees Capital Purchase ( #66005)
Purpose of Expenditure (Check Appropriate):
Cost:
Scheduled replacement
Number of units requested:
1
Present equipment obsolete
Replace worn -out equipment
Per Unit Total
Improve procedures, records, etc.
Purchase Price
2,100,000.00 $ 2,100,000.00
Increased safety
Plus: Installation or other costs
$
X
Construction/Major Improvement
Less: Trade -in or other discount
$
Other (Please specify)
Net Purchase Cost
Estimated Useful Life in Years:
Funding Source (List Amount):
$ 2,100,000.00 $ 2,100,000.00
Replaced item(s):
Item
Disposition Method
Village
Lease
2,100,000.00 Grant
Developer Fees
Debt Service
Other
Operating Impact:
Project will be detennined by grantfunding
Other Comment:
Capital Check (Please enter your selection # from the choices provided below):
Enter Selection #
Capital Category
Capitalization Threshold Capital Outlay?
5 year CIP?
1
Land Improvement
25,000 Yes
Include in CIP
Selection #:
Capital Category:
Capitalization Threshold:
1
Land Improvement
25,000
2
Building
50,000
3
Building Improvement
50,000
4
Machinery & Equipment
5,000
5
Vehicle
5,000
6
Infrastructure
250,000
FY 2015 Proposed Budget Page 275 of 297
Village of North Palm Beach
5 Year Capital Improvement Plan
FY 2015 -2019
Fund: Country Club Department: All Departments Division: All Divisions
Cost by CIP year
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Description
Current Inventory
Estimated Life
Automotive:
Beverage Cart
2013(l)
4 years
15,000
$ 15,000
Golf carts w/ GPS systems
2013 (80)
3 years
440,000
$ 440,000
Carry Alls
2013 (2)
3 years
18,000
$ 18,000
Driving Range Cart
2014(l)
4 years
11,000
$ 11,000
SuhtotalAutomotive
458,000
26,000
$ 484,000
Machinery & Equipment:
Suhtotal Machinery & Equipment
-
-
$
Construction and Major Renovation:
Country Club Parking Lot
2011
10 years
$
$
Suhtotal Construction and Major Renovation
$ -
Estimated Total Cost $ $ 458,000 $ $ 26,000 $ $ 484,000
Funding Source
FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Total
Budget Year (Year # 1) (Year # 2) (Year # 3) (Year # 4) (Year # 5)
Village
26,000
$ 26,000
Grant
$ -
Lease
458,000
$ 458,000
Estimated Total Funding
$
$ 458,000
$
$ 26,000
$
$ 484,000
Annual Operating Cost Increases Created by Project: $
Description of Operating Impact: No operating impact
FY 2015 Proposed Budget Page 276 of 297